What legal issues often arise?
There are several key issues to be negotiated in most transactions, including:
- Who installs the apparatus?
The installation of the apparatus is often very expensive. If the ESCO pays, it will have calculated that its investment will come good once the development is occupied by a certain number of end users. If, however, the scheme is unsuccessful then its risk will not pay off. It is therefore not uncommon for the developer to agree to pay for the initial installation and then for the ESCO to reimburse these costs as the development is built out and occupied
The ESCO is usually responsible for maintaining and repairing the system, and sometimes for providing an alternative temporary power supply if the system breaks down. Various issues stem from these obligations, including:
- What if the tenants damage the system?
- If the CHP system fails and the ESCO has to supply alternative power, it will need a licence from the developer to locate often diesel-powered generators on site for however long it takes to repair the original CHP.
- The extent to which the ESCO is liable to compensate the tenants for a failure to supply tenants by way of service credits, which may be a capped sum. In reality, tenants do not have an option to source heating or hot water elsewhere as they have no gas supplies. A complete failure of the system, system leaks or a system which yields heating and hot water at more than the market rate, can lead to sales problems and reputational damage for the developer.
- Often the developer will require lift and shift rights to ensure that it can relocate the apparatus in the event of any potential redevelopment, the costs of which will typically be borne by the developer in full.
- Ownership of the apparatus
The question of status of legal ownership in the apparatus itself also underpins the financial viability of these schemes for developers and investors, with legal ownership dictating the analysis around certain tax treatment (such as the availability of capital allowances). The ability to transfer ownership to a third party is also enhanced by the asset-owning entity retaining an interest in land which can be transferred or "conveyed" in the land-law sense. The outcome of this question will depend on the facts in each case but often it is agreed that the apparatus becomes a tenant's fixture once installed.
- What land rights will the ESCO have?
District heating pipes do not currently benefit from the same type of statutory regime which protects the traditional utilities (such as electricity, gas, telecoms and water). Easements and wayleaves have historically been the norm for granting the necessary legal rights in land for the installation, maintenance and repair of apparatus for those utilities (with the statutory protections offering a fallback position), but the lack of statutory protection for district heating, coupled with the increased interest in this asset class from institutional investors (including pension funds, private equity funds and financial institutions), has seen a shift in demand towards more robust proprietary interests in the land in which the apparatus is installed. It is now not uncommon for developers to grant 30-40- year leases of the relevant underground area to the asset- owning entities, which are then registered at HM Land Registry. This offers investors a registered legal interest in land which can be charged to financiers, who can in turn protect this security by registration at the Land Registry.
What legal structure is put in place when a CHP system is installed?

Documentation in a CHP scheme includes:
- The master concession agreement between the developer and the ESCO, under which the developer grants the ESCO a concession to operate the CHP system, typically for 30-40 years. The developer will covenant to build an energy centre shell on site and the secondary network within the buildings, and to procure that the end users enter into the ESCO's standard form heat supply agreements with the will covenant to:
- install the CHP system in the energy centre;
- construct the primary network of pipes and adopt the secondary network of pipes once constructed;
- provide heating to the occupiers, often on the basis of an agreed price formula which will reflect the fluctuations in the price of gas but which should always be cheaper than the end users running their own boilers;
- repair and maintain the system; and
- provide alternative temporary power in the event of a system failure.
- The developer and ESCO may each sub-contract their obligations to specialist contractors, in which case there will be a series of sub-contracts.
- Individual heat supply agreements between the ESCO and the end users. This will oblige the occupiers to pay for the supply of heating, and for the ESCO to compensate tenants for any failure to supply.
- A supply agreement between the ESCO and the gas supplier.
- There may also be a third party property-owning company which will own| or adopt the energy centre, any temporary energy centre, both the primary and the secondary networks and the HIUs.
- Land agreements - this will usually take the form of a lease of the energy centre, and a series of legal easements and/or leases of the underground/internal channels in which the pipe networks are to be located.
Future potential
The use of CHP systems and the installation of district heating systems is growing in popularity for developers and end-users but also for investors as an investment class. It is a relatively new system in the UK, so the physical plant and network, and the contractual arrangements that regulate the relationships, are still evolving and need careful consideration at the outset of any development proposal.
This article was first published in the Estates Gazette on 30 August 2017.